Installation For Ultrafine Foller Mill

  • The maintenance of the Raymond mill is a very important and regular work. It should be closely coordinated with the operation and maintenance of the machine.

    1. The equipment shall be installed on a horizontal concrete foundation and fixed with anchor bolts.

    2. During installation, attention should be paid to the vertical between the main body and the horizontal body.

    3. After installation, check whether the bolts in all parts are loose and whether the main engine warehouse door is tightened. If so, please tighten it.

    4. Power line and control switch are configured according to the power of the equipment.

    5. After the inspection, carry out empty load test. If the test is normal, the production can be carried out.