Modular HCL Tail Gas Scrubber

  • click to rate

    Modular HCL Tail Gas Scrubber

    Project Name

    45000m3/h HCL tail gas scrubber

    25000m3/h HCL tail gas scrubber

    Location

    Daman, Saudi Arabia

    Time

    November, 2014

    Client

    Steel wire rope manufacturer

    Scope of work

    EPC

    PCC provides EPC service, including process engineering design, pipe match, equipment design
    & manufacture, electrical appliance & meter installation, site installation guidance, commissioning
    and startup, training etc.

    Description

    The client provided the tail gas component and the local emission requirements. The discharge tail
    gas content is much lower than local emission standard This project was delivered within 45 days,
    finished installation and commissioning in 5 days.

    Evaluation

    The plant is running stably since started in November, 2014. The client is very satisfied, and develop
    long term cooperation with PCC.